Short Description:

1. Construction method
According to the actual situation of the demolition site, on-site survey, through multi-party research and analysis comparison, combined with previous construction experience, the chimney demolition decided to adopt the method of erecting a circular wall scaffolding, manually using the wind pickaxe to disassemble the chimney from top to bottom one by one, dismantling the construction plan of free landing in blocks, dismantling the chimney barrel body to +15m in turn, and the remaining 15m barrel body was crushed by excavator.
2. Preparation before construction
Before the construction of the demolition project, master the 80m chimney construction drawings and construction plan, and understand the division of the adjacent building. Take protective measures for pipelines and facilities that need to be retained. The specific measures are as follows:
Due to the large number of buildings and pipelines around the chimney to be demolished, the operating platform shall be closed during the demolition work, and no gravel shall be splashed outward (except dust).


  • Chimney construction price: $1000 - $3000/m
  • Min.Order Quantity: 100 Piece/Pieces
  • Supply Ability: worldwide
  • Product Detail

    Hongshun Construction

    Product Tags

    1. Construction method
    According to the actual situation of the demolition site, on-site survey, through multi-party research and analysis comparison, combined with previous construction experience, the chimney demolition decided to adopt the method of erecting a circular wall scaffolding, manually using the wind pickaxe to disassemble the chimney from top to bottom one by one, dismantling the construction plan of free landing in blocks, dismantling the chimney barrel body to +15m in turn, and the remaining 15m barrel body was crushed by excavator.
    2. Preparation before construction
    Before the construction of the demolition project, master the 80m chimney construction drawings and construction plan, and understand the division of the adjacent building. Take protective measures for pipelines and facilities that need to be retained. The specific measures are as follows:
    Due to the large number of buildings and pipelines around the chimney to be demolished, the operating platform shall be closed during the demolition work, and no gravel shall be splashed outward (except dust).


  • Previous:
  • Next:

  • “Hongshun Construction Engineering Co., Ltd.” is a large-scale comprehensive construction enterprise integrating civil engineering, anti-corrosion, thermal insulation and steel structure. Specializing in aerial work, including new construction, maintenance, anti-corrosion, landscaping painting, demolition and other construction projects of towering structures (chimneys, hyperbolic cooling towers, ash storage silos).